See scheduled finish date

This term is defined in the 3rd edition of the PMBOK but not in the 4th.

Related Entries:

 

  • Scheduled Finish Date (SF)  In project management, Scheduled Finish date (SF) or planned finish date, is the date and time work was scheduled...
  •  
  • Finish Date The term finish date refers specifically to the date in which the particular schedule activity as part of the overall...
  •  
  • Planned Start Date See scheduled start This term is defined in the 3rd edition of the PMBOK but not in the 4th. ...
  •  
  • Baseline Finish Date  The term baseline finish date applies to the date on which a schedule activity is expected to be completed...
  •  
  • Current Finish Date The term current start date refers to the deliberate and calculated estimate of the specific point in time at which...