The term late finish date, in terms pf project management, refers specifically to a specific point of time that takes place as part of the Critical Path Method. The particular point in time can specifically be designated as the latest point that could possible occur at which the designated schedule work activity in question can and may be completed based on the previously determined network schedule logic, the project completion date that has already been discussed and determined, and any predetermined constraints or limitations that the project team has determined may exist in relation to the project. This date represents the latest point at which the activity may be concluded without committing a violation in the previously dictated schedule constraints or without casing delays in the project completion date. The determination of the late finish date takes place through the calculation of the backward pass of the project schedule network in question.

This term is defined in the 3rd and the 4th edition of the PMBOK.

Related Entries:

 

  • Late Start Date  The term late start date, in terms pf project management, refers specifically to a specific point of time that...
  •  
  • Scheduled Finish Date (SF) In project management, Scheduled Finish date (SF) or planned finish date, is the date and time work was scheduled to...
  •  
  • Early Finish Date The phrase early finish date (also known by the abbreviation EF) refers, on the critical path method, to the earliest...
  •  
  • Finish Date The term finish date refers specifically to the date in which the particular schedule activity as part of the overall...
  •  
  • Current Finish Date The term current start date refers to the deliberate and calculated estimate of the specific point in time at which...