Finish-to-finish, also known by the two letter abbreviation of FF, refers to the particular and specific long term and logical relationship exists between one particular schedule activity and another particular schedule activity. In this relationship, the succeeding activity cannot finish until the preceding activity has ultimately been concluded. In some instances, the finish to finish estimation can take place at the start of the project. The project team can do a careful analysis of all of the estimated finish dates for the entire listing of schedule events that will take place throughout the life of the project. Then , the finish to finish for each individual gap of schedule activities can then be determined by subtracting the start date of one specific schedule activity from the end date of the preceding one. Additionally, the finish to finish can be modified by adjusting the expected start date of one following activity or attempting to modify the finish date of the preceding activity.

This term is defined in the 3rd and the 4th edition of the PMBOK.

Related Entries:

 

  • Current Finish Date  The term current start date refers to the deliberate and calculated estimate of the specific point in time at...
  •  
  • Finish-to-Start The term finish to start refers specifically to the logical relationship that exits between the activities that make up he...
  •  
  • Scheduled Finish Date (SF) In project management, Scheduled Finish date (SF) or planned finish date, is the date and time work was scheduled to...
  •  
  • Lag The short three letter term lag refers specifically to the project management technique that refers to the logical relationship that...
  •  
  • Network Open End The project management phrase network open end refers specifically to any particular schedule activity that occurs and takes place in...