Baseline Start Date

The term baseline start date applies to the actual scheduled start date of a schedule activity within the approved schedule baseline. The baseline start date will typically be estimated at the onset of a schedule activity based on a determination of how much work needs to be done, how many team members will be required to complete it, which specific team members should be involved in the process (and concurrently what their schedules may look like in regards to availability), and what resources may be needed. The baseline start date may be adjusted prior to n activity’s kickoff if it has become apparent that delays in preceding activities will make the previously determined baseline start date impossible to meet. Provided the project team is able to secure the necessary approvals to do so, the baseline start date can be modified based on the requirements necessary. See also scheduled start date.

This term is defined in the 3rd edition of the PMBOK but not in the 4th.

Related Entries:
     
  • Baseline Finish Date  The term baseline finish date applies to the date on which a schedule activity is expected to be completed...
  •  
  • Scheduled Start Date (SS) The Scheduled Start Date (SS), also called the Planned Start Date, is the planned beginning of work on an assignment....
  •  
  • Start Date A start date of a project is sometimes determined by the expected completion date. If a project is to be...
  •  
  • Late Start Date The term late start date, in terms pf project management, refers specifically to a specific point of time that takes...
  •  
  • Actual Start Date (AS) Effective Project Management depends largely on keeping track of Actual Start Dates to determine productivity. The Actual Start Date marks...

Leave a Comment